Monday, June 6, 2011

week 13.








Most of the work accomplished was by Mike Blanc himself over the weekend. Carpenter Dave Grimm was not at the house this week, and Matt Anderson continued with the vent work in the attic but only for a couple days. Everyone is waiting for Renz Plumbing & Electric to get the plumbing installed which will get a lot of things in motion.

Mike repaired the garage door and moved all of his tools to the basement. He also removed the heavy, cast iron stairs piece by piece so that they can be sand blasted and re-set. The iron support system under the stair treads was almost completely deteriorated and Mike will have it re-engineered & built. He also cleaned out years & years of debris from under the porch and stairs. (Glad it wasn't my job!)

No comments:

Post a Comment