It was a big week at The Big House. Besides having Magill Restoration start the tuckpointing process,




  • We had the footings poured and foundation bricks laid for the new mudroom by Knoell Masonry



  • "Slick" Dixon poured the concrete flooring in the new mudroom



  • Mike got the dirt moved out of the basement with his team of young bucks



  • Dave Grimm got the basement walls framed up and basement stairs installed (with temporary treads)



(Next-to-last photo shows future Laundry Room with future Sewing Room behind. Bottom photo shows future Playroom with future Storage Room behind.)